Installation of the New Parliament with assembly building Phase2, the D–ticket Project of State Railway of Thailand and the Construction Project of information center building of the Department of Lands, etc
received more automated system work, thus unable to control the installation time as projected in some projects. - Other income decreased 88.05% from the same period of last year due to in 2017, the Company
to The company has an automated system that is never done before, so it is not possible to control the installation time as expected. - Other income decreased 88.46% from the same quarter of last year
network with total project value of Baht 125.00 million. Under the contract, the project was due to complete in February 2018. Nevertheless, during installation, the installation areas were continuously
2020 The Company recognizes revenue from the production line installation project and the production line test for the whole system installation, which is expected to be installed in May 2020, resulting
installation of the production line and the testing of the production line in respect of the installation of the entire production line, which was installed successfully. In July 2020, the results of the
project value of Baht 125.00 million. Under the contract, the project was due to complete in February 2018. Nevertheless, during installation, the installation areas were continuously affected by floods
steam boiler and balance of plants including manufacturing and installation 3. Registered Capital: 25,000 EUR or equal to 901,052.50 Baht (Average selling rate on 4th April 2019: 36.0421 Baht per Euro
27.63 million and THB 2.23 million respectively or equivalent to 297.10% and 314.08% respectively due to installation solar cell project 1 MW and warehouse tenants increased. Gross Profit / Margin The
million Baht compared to 38.67 million Baht and 38.41 million Baht respectively in the quarter 2/2016 due to the major reasons as follows; 1. Incomes from the production and installation of the pipeline