completed and the construction of various buildings has progressed by more than 84.63% of the total construction. At present, the project is in the process of the development of utility system including the
completed and the construction of various buildings has progressed by more than 84.63% of the total construction. At present, the project is in the process of the development of utility system including the
Directors’ Meeting No. 5/2018 and PF Board of Directors’ Meeting No. 9/2018. The construction of Carnival Magic Project has progressed by about 98.56% of the total construction, or 84.63% of the total
intended to strengthen the capacity, expertise and international competitiveness of financial markets and the funds industry in the region.Implementation ProgressThe participating economies have progressed
the project has progressed 99.84% (The construction plan was 100%). Consequently, the project was completed and its operation started on July 20, 2017. - Banpong Utilities Company Limited, (EGCO holds a
Renewable Energy Certificates (REC) concerning its electricity generation output. The construction of the project has progressed 97.99% (The construction plan was 97.46%). The commercial operation date is
progressed 91.58% (The construction plan was 91.70%). The commercial operation date is scheduled in the fourth quarter of 2019. - SBPL Project, a project of San Buenaventura Power Ltd., Co., (EGCO holds a 49
Electricite Du Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 98.78% (The construction plan was 98.30%). The commercial operation date is scheduled
with EGAT with the contracted capacity of 1,220 MW and Electricite De Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 94.37% (The
with EGAT with the contracted capacity of 1,220 MW and Electricite De Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 96.36% (The