Cogen, with the installed capacity of 115 MW. The project is located in Klongnueng sub-district, Klonglaung district, Pathumthani province. TJ Cogen has entered into the PPA with EGAT for 25 years with
Renewable Energy Certificates (REC) concerning its electricity generation output. The construction of the project has progressed 97.99% (The construction plan was 97.46%). The commercial operation date is
cogeneration power plant project. The power plant has an installed capacity of 121 MW. The project is located in Klongnueng sub-district, Klonglaung district, Pathumthani province. The project has entered into
-year feed-in tariff PPA, for the sale of electricity by the project with the contracted capacity of 640 MW. The construction of the project has progressed 60.67% (The construction plan was 62.95%). The
progressed 91.58% (The construction plan was 91.70%). The commercial operation date is scheduled in the fourth quarter of 2019. - SBPL Project, a project of San Buenaventura Power Ltd., Co., (EGCO holds a 49
Electricite Du Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 98.78% (The construction plan was 98.30%). The commercial operation date is scheduled
with EGAT with the contracted capacity of 1,220 MW and Electricite De Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 94.37% (The
with EGAT with the contracted capacity of 1,220 MW and Electricite De Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 96.36% (The
Certificates (REC) concerning its electricity generation output. The construction of the project has progressed 91.55% (The construction plan was 91.52%). The commercial operation date is scheduled in the fourth
., Co., (EGCO holds a 49% ownership interest.), is a 500 MW supercritical coal-fired power plant, in Mauban, Quezon province of Republic of the Philippines. 455 MW of the plant’s capacity and energy are