the project has progressed 99.84% (The construction plan was 100%). Consequently, the project was completed and its operation started on July 20, 2017. - Banpong Utilities Company Limited, (EGCO holds a
Renewable Energy Certificates (REC) concerning its electricity generation output. The construction of the project has progressed 97.99% (The construction plan was 97.46%). The commercial operation date is
net profit* margin of 13.7%, +110 bps YoY. Our strategies are to focus on core products and defend profit through supply chain, operation costs and expenses control, such that A&P have been cut or
progressed 91.58% (The construction plan was 91.70%). The commercial operation date is scheduled in the fourth quarter of 2019. - SBPL Project, a project of San Buenaventura Power Ltd., Co., (EGCO holds a 49
Electricite Du Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 98.78% (The construction plan was 98.30%). The commercial operation date is scheduled
with EGAT with the contracted capacity of 1,220 MW and Electricite De Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 94.37% (The
with EGAT with the contracted capacity of 1,220 MW and Electricite De Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 96.36% (The
Certificates (REC) concerning its electricity generation output. The construction of the project has progressed 91.55% (The construction plan was 91.52%). The commercial operation date is scheduled in the fourth