rendered a judgement in the Red Case No. Por. 5396/2562, wherein the defendant was required to pay (1) a civil penalty, 1.25 times the benefits that the defendant received or would have received from
information to sell IFEC shares, to pay civil penalty and compensation for the benefits gained from committing the offense. However, Suphanan did not agree to comply with the civil sanction. Later, on 27
network with total project value of Baht 125.00 million. Under the contract, the project was due to complete in February 2018. Nevertheless, during installation, the installation areas were continuously
consists of penalty amounting to Baht (18.90) million, additional cost of project of Baht (3.86) million, and revision of project budget equal to Baht (8.40) million. 1.2 Many projects have realized progress
Mr.Boonchoke Thiratarakorn . 31/10/2024 agreed to comply with civil penalties determined by the Civil Penalty Committee as follows : - a civil monetary penalty of
Mr. Booncherd Santudpanich . 31/10/2024 agreed to comply with civil penalties determined by the Civil Penalty Committee as follows : - a civil monetary penalty of
Mr. Suwit Jiraphongtrakul . 31/10/2024 agreed to comply with civil penalties determined by the Civil Penalty Committee as follows : - a civil monetary penalty of
Mrs. Wanna Sittisirinukul . 31/10/2024 agreed to comply with civil penalties determined by the Civil Penalty Committee as follows : - a civil monetary penalty of
Mr. Preyatada Buranaworakhun . 31/10/2024 agreed to comply with civil penalties determined by the Civil Penalty Committee as follows : - a civil monetary penalty
Mr. Surachaste Boonyasatian . 31/10/2024 agreed to comply with civil penalties determined by the Civil Penalty Committee as follows : - a civil monetary penalty