completed and the construction of various buildings has progressed by more than 84.63% of the total construction. At present, the project is in the process of the development of utility system including the
completed and the construction of various buildings has progressed by more than 84.63% of the total construction. At present, the project is in the process of the development of utility system including the
Directors’ Meeting No. 5/2018 and PF Board of Directors’ Meeting No. 9/2018. The construction of Carnival Magic Project has progressed by about 98.56% of the total construction, or 84.63% of the total
long-term returns. In 2019, CPN progressed with the following asset enhancement initiatives. Renovation programs of existing malls are under way and expects to be completed in 2019 comprising a