pandemic on the goods deliveries including inbound and outbound shipments to customers getting stranded and delayed during this period. In addition, the delayed deliverables at several of L&E‘s completed
had an extra expenses from a delayed project. Those expenses were composed of both a fine from the delayed project (19.00) million baht and extra cost for the delayed project (3.76) million baht. 2.2 In
previous year, as a consequence of the performance of Advance Power Conversion Company (APCON) performance whose projects had been delayed from the plan resulted in net loss in 2018. Earnings before tax (EBT
85.76% from Q1 year 2017. The reason was the delay on the shipment to customers in the first two months of year 2018. The main raw materials’ crop, which is sweet corn, was delayed due to the weather. The
delayed orders from one major customer in this quarter, but the repeated order will be placed in the next quarter. 2. The company’s consolidated net loss for the period (Q.1) amount -11.20 Million Baht
consisting of Interest expense from bank creditors amount of 23.42 million baht, interest on short-term loans amount of 1.63 million baht, interest of debentures amount of 21.74 million baht, delayed interest
quarter of 2017, customers were unable to install due to heavy rain and flooding. Delayed delivery and installation resulted in Q3 2017 performance as follows; - Decreased on sales from Baht 305.90M in
to replace the less energy efficient ones in order to conserve energy, but this year the Retail Chain had delayed the investments. Profit for the period The Company's profit of the quarter was 3.3
(loss): A slump in shares of profits by 390% from the same period of the previous year was solely due to a negative performance of Advance Power Conversion Company (APCON) whose projects had been delayed
out to customers during this period and therefore making goods delivery delayed next quarters accordingly. Profit for the period L&E’s consolidated profit for the period of Q1/2020 was posted at Baht