progressed 62.79% (The construction plan was 62.55%). The commercial operation date is scheduled in the second quarter of 2022. Page 3 1.2 Additional Investments in Joint Ventures - On September 25, 2019, EGCO
long-term returns. In 2019, CPN progressed with the following asset enhancement initiatives. Renovation programs of existing malls are under way and expects to be completed in 2019 comprising a
completed and the construction of various buildings has progressed by more than 84.63% of the total construction. At present, the project is in the process of the development of utility system including the
completed and the construction of various buildings has progressed by more than 84.63% of the total construction. At present, the project is in the process of the development of utility system including the
Directors’ Meeting No. 5/2018 and PF Board of Directors’ Meeting No. 9/2018. The construction of Carnival Magic Project has progressed by about 98.56% of the total construction, or 84.63% of the total
the project has progressed 99.84% (The construction plan was 100%). Consequently, the project was completed and its operation started on July 20, 2017. - Banpong Utilities Company Limited, (EGCO holds a
increased from business expansion. For the 9M/2018, the net profit improved by Baht 420 million or 17% from 9M/2017. The gain was primarily due to start-up of IRPC-CP Phase 2 and ISP1 in Q4/2017 and the
Renewable Energy Certificates (REC) concerning its electricity generation output. The construction of the project has progressed 97.99% (The construction plan was 97.46%). The commercial operation date is
-CP Phase 1 ceased the generators to commission with Phase 2 in preparation to start the Commercial Operation Date (COD) of both phases which also caused the drop in the revenue. The drop in revenue of
Financial Management Purposes (Treasury Stocks) . Since the start of the program until the 30th December 2019, the cumulative number of shares repurchased was 16,492,800 shares, with the total value of THB