quarterly income derived from sales, ended on 31 March 2019, is 28.32 million baht, caused by the subsidiary, Grace Water Mate Co., Ltd. (“GWM”), running the business of kidney cleanser and medical supplies
to the COD of both phases of IRPC-CP since 15 November 2017. Due to the fact that, Q1/2018 was the first full quarter of both phases running at full capacity. 14 ผลประกอบ การบริษัท IRPC Clean Power
the project has progressed 99.84% (The construction plan was 100%). Consequently, the project was completed and its operation started on July 20, 2017. - Banpong Utilities Company Limited, (EGCO holds a
., Ltd. (“GWM”), running the business of kidney cleanser and medical supplies manufacturing and distribution, which is increase from the same quarter of the previous years for 32.58 million baht (38.59
Renewable Energy Certificates (REC) concerning its electricity generation output. The construction of the project has progressed 97.99% (The construction plan was 97.46%). The commercial operation date is
progressed 91.58% (The construction plan was 91.70%). The commercial operation date is scheduled in the fourth quarter of 2019. - SBPL Project, a project of San Buenaventura Power Ltd., Co., (EGCO holds a 49
Electricite Du Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 98.78% (The construction plan was 98.30%). The commercial operation date is scheduled
with EGAT with the contracted capacity of 1,220 MW and Electricite De Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 94.37% (The
with EGAT with the contracted capacity of 1,220 MW and Electricite De Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 96.36% (The
Certificates (REC) concerning its electricity generation output. The construction of the project has progressed 91.55% (The construction plan was 91.52%). The commercial operation date is scheduled in the fourth