amount of THB 3.55 million (2 installments). The remaining amount to be paid upon the Agreement is THB 5.33 million. Currently, hydraulic platform construction work has progressed to around 50 percent. 4
ICO, the SEC would like to further raise the following issues for public consultation. Please note that our public consultation will be extended to December 15, 2017. To send your comments and
the project has progressed 99.84% (The construction plan was 100%). Consequently, the project was completed and its operation started on July 20, 2017. - Banpong Utilities Company Limited, (EGCO holds a
Renewable Energy Certificates (REC) concerning its electricity generation output. The construction of the project has progressed 97.99% (The construction plan was 97.46%). The commercial operation date is
progressed 91.58% (The construction plan was 91.70%). The commercial operation date is scheduled in the fourth quarter of 2019. - SBPL Project, a project of San Buenaventura Power Ltd., Co., (EGCO holds a 49
Electricite Du Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 98.78% (The construction plan was 98.30%). The commercial operation date is scheduled
with EGAT with the contracted capacity of 1,220 MW and Electricite De Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 94.37% (The
with EGAT with the contracted capacity of 1,220 MW and Electricite De Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 96.36% (The
Certificates (REC) concerning its electricity generation output. The construction of the project has progressed 91.55% (The construction plan was 91.52%). The commercial operation date is scheduled in the fourth