events in the second Quarter of 2017 The progress in construction projects - Klongluang Utilities Company Limited, (EGCO holds a 99.99% ownership interest.), is a cogeneration power plant project, TJ
Energy Services Co.,Ltd. (Paju ES) (EGCO holds a 49.00% ownership interest), located in Gangdong-gu, Seoul, South Korea with a capacity of 19.80 MW. Gangdong will sell electricity to Korea Electric Power
. Significant events in the third Quarter of 2017 1.1 The progress in construction projects 1.1.1 Project completion - Klongluang Utilities Company Limited, (EGCO holds a 100% ownership interest.), is a
Xayaburi Power Company Limited, (EGCO holds a 12.50% ownership interest.), is a hydro power plant project, Run-of-River. The project is located in the Laos People’s Democratic Republic (Laos PDR). The
events in the first Quarter of 2019 1.1 The progress in construction projects - Xayaburi Project, a project of the Xayaburi Power Company Limited, (EGCO holds a 12.50% ownership interest.), is a hydro
ES) (EGCO holds a 49.00% ownership interest), located in Gangdong-gu, Seoul, South Korea with a capacity of 19.80 MW. Gangdong will sell electricity to Korea Electric Power Corporation (KEPCO), the
, (EGCO holds a 12.50% ownership interest.), is a hydro power plant project, Run-of-River. The project is located in the Laos People’s Democratic Republic (Laos PDR). The project has entered into the PPA
, (EGCO holds a 12.50% ownership interest.), is a hydro power plant project, Run-of-River. The project is located in the Laos People’s Democratic Republic (Laos PDR). The project has entered into the PPA
), a project of Paju Energy Services Co.,Ltd. (Paju ES) (EGCO holds a 49.00% ownership interest), located in Gangdong-gu, Seoul, South Korea with a capacity of 19.80 MW. Gangdong will sell electricity to
, (EGCO holds a 12.50% ownership interest.), is a hydro power plant project, Run-of-River. The project is located in the Laos People’s Democratic Republic (Laos PDR). The project has entered into the PPA