accomplishment of cost management policy, 2 | MANAGEMENT DISCUSSION AND ANALYSIS FOR THE YEAR 2020 • Gross margin: UWC has recorded gross margin since Q1-2020 due to accomplishment of cost management policy
until the accomplishment of the full installed capacity as planned of which it is scheduled to be completed by the end of 2024. However, the Joint Venture is under the further negotiation with the joint
the project has progressed 99.84% (The construction plan was 100%). Consequently, the project was completed and its operation started on July 20, 2017. - Banpong Utilities Company Limited, (EGCO holds a
by 36.1 percent form Q4-2016 because the project has already been delivered and recognized the accomplishment of the project completed rather than those in Q4-2016, due in 2017 the government has
by 36.1 percent form Q4-2016 because the project has already been delivered and recognized the accomplishment of the project completed rather than those in Q4-2016, due in 2017 the government has
transmission and telecommunication tower ratio in Q1-2020 decreased by 43.59% QoQ resulting from accomplishment of cost management policy, • Cost to revenue from sale of electricity ratio in Q1-2020 dropped by
Renewable Energy Certificates (REC) concerning its electricity generation output. The construction of the project has progressed 97.99% (The construction plan was 97.46%). The commercial operation date is
transmission and telecommunication tower ratio in Q1-2020 decreased by 43.59% QoQ resulting from accomplishment of cost management policy, Cost to revenue from sale of electricity ratio in Q1-2020 dropped by
progressed 91.58% (The construction plan was 91.70%). The commercial operation date is scheduled in the fourth quarter of 2019. - SBPL Project, a project of San Buenaventura Power Ltd., Co., (EGCO holds a 49
Electricite Du Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 98.78% (The construction plan was 98.30%). The commercial operation date is scheduled