construction projects that are being completed. In some projects, the owners have delayed in the work area handover which prohibit the work. The construction area handover is expected to commence and the work
increase of 463.3 MB and 700.2 MB or increase of 36.6% and 68.0%, respectively. This is because the Company had delivered many large-scale projects which had just been auctioned in early 2019. Those large
recovered back since the beginning of the second quarter. In addition, the company recognized the revenue from project work decreased by 28.56 million baht since most of the work was completed since last year
157.0 MB and 221.6 MB, respectively. This is because the Company had delivered many large-scale projects which had just been auctioned in Q1–2019. In fact, those large-scale projects had delayed their
accordance with the second paragraph shall be completed within three months from the end of each accounting period. For each financial year, such preparation shall be completed within twenty-one days from the
a result, in Quarter 1’ 2019, has orders in large projects, such as the wastewater treatment equipment installation project. While in the first quarter of 2018, the large project income has just begun
project such as Industrial water supply system, Pre Treatment system etc. and we start recognize revenue from these projects in each Quarter of 2019 while in the year 2018 the Company has just started
decline in export revenue from Japan customers, resulting in if considered especially for the 2nd quarter of 2020, it showed the sales revenue just slightly decreased. For other income, during the 1st
Property Business: the Company will be able to record the revenue from sales of residential condominium units in the statement of comprehensive income when the real estate project has been completed and
system and we start recognize revenue from this project in this Quarter while the same period of previous year the Company has just started adjustment of the business strategy to focus on the large project