, machinery, office equipment, vehicles, right of use and work on progress of construction: As at and 30th September 2020 and 31st March 2020, the Company and its subsidiaries had Land, plant and equipment
, machinery, office equipments, vehicles and work on progress of construction: As at 30th September and 31st March 2019, the Company and its subsidiaries had Land, plant and equipments – net of Baht 538.16
Management Discussion and Analysis 1. Significant events in the third Quarter of 2019 1.1 The progress in construction projects 1.1.1 Project completion - SBPL Project, a project of San Buenaventura Power Ltd
. Advance payments for constructions and purchase of fixed assets decreased by Baht 54.4 million from Krabi Solid Waste Power Plant which some progress was done during the period. Rights to service under
decreased by Baht 36.2 million from Krabi Solid Waste Power Plant, which partially progress is done during the period. Rights to service under concession arrangements increased by Baht 508.2 million from
from Krabi Solid Waste Power Plant, which partially progress is done during the period. Rights to service under concession arrangements increased by Baht 712.7 million from concession rights of Krabi
the compensation in 2 projects at installed capacity 30 MW per project. The Group submitted the lawsuit since 2020 and, at present, the lawsuit still in the progress of consideration of the Central
at the end of 2021, the Company does not have large project that requires a lot of investment compared to the end of 2020 which is a large project in progress. Therefore, the purchase of goods and
at the end of 2021, the Company does not have large project that requires a lot of investment compared to the end of 2020 which is a large project in progress. Therefore, the purchase of goods and
projects at installed capacity 30 MW per project. The Group submitted the lawsuit since 2020 and, at present, the lawsuit still in the progress of consideration of the Central Administrative Court