along with 13 tonnes per hour of steam output. The project is extendable for up to an additional every 2 years. Construction works of the project was completed and its operation started on July 20, 2017
, Ratchaburi Province, has approximately 100 megawatts electricity generating capacity and steam generating capacity of 15 tons per hour. It The Project has 25-year Firm Cogeneration PPA with Electricity
35 percent. Management Discussion and Analysis For the Year Ended December 31, 2017 Page 4 Berkprai Cogeneration SPP Project has approximately 100 megawatts electricity generating capacity and steam
363.4 413.9 (50.5) (12.2) Sales of electricity to Industrial Users (IU) 1.6 2.3 (0.7) (30.4) Sales of steam (IU) 4.9 4.1 0.8 19.5 Total sales from Natural Gas Power Plant 470.8 522.6 (51.8) (9.9) Sales of
plants to produce electricity and/or steam using renewable and/or non renewable energy resources , for captive consumption and/or for wholesale; electric power transmission and distribution,” The Board of
Power Plant On June 1, 2019, Berkprai Cogeneration SPP Power Plant with power generation capacity of approximately 100 megawatts and steam generation capacity of approximately 15 tons per hour, located in
generated power and steam will be sold to industrial customers and the COD is scheduled in July 2023. Tri Energy Power Plant On June 30, 2020, the 720-magawatt Tri Energy Power Plant in Ratchaburi Province
approximately THB 2,176 million. The generated power and steam will be sold to industrial customers and the commercial operation is scheduled in July 2023. On April 21, 2020, the three shareholders have already
363.4 413.9 (50.5) (12.2) Sales of electricity to Industrial Users (IU) 1.6 2.3 (0.7) (30.4) Sales of steam (IU) 4.9 4.1 0.8 19.5 Total sales from Natural Gas Power Plant 470.8 522.6 (51.8) (9.9) Sales of
service under a Power Purchase Agreement 411.5 363.4 388.0 6.8% (5.7%) 825.3 751.4 (9.0%) Sales of electricity to Industrial Users (IU) 1.8 1.6 1.3 (18.8%) (27.8%) 4.1 2.9 (29.3%) Sales of steam (IU) 3.3