Ref: CIG 040/2020 November 16, 2020 Subject: Profit and loss reporting for the period of 9 month of 2020 and explanation of more than 20 percent fluctuation in profit and loss compared to that of
exchange rate also decreased compared to the prior period since the company has planned to hedge into the forward contracts to reduce the risks from the fluctuation of exchange rate. Finance Cost In the
progressed 91.58% (The construction plan was 91.70%). The commercial operation date is scheduled in the fourth quarter of 2019. - SBPL Project, a project of San Buenaventura Power Ltd., Co., (EGCO holds a 49
Electricite Du Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 98.78% (The construction plan was 98.30%). The commercial operation date is scheduled
with EGAT with the contracted capacity of 1,220 MW and Electricite De Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 94.37% (The
with EGAT with the contracted capacity of 1,220 MW and Electricite De Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 96.36% (The
Certificates (REC) concerning its electricity generation output. The construction of the project has progressed 91.55% (The construction plan was 91.52%). The commercial operation date is scheduled in the fourth
investment in subsidiary of 12 million Baht and allowance for doubtful accounts of 2.78 million Baht. The fluctuation of CPO price mentioned above had reflected the Company's business operation in the
fluctuation of CPO price since sometime the Company is unable to adjust its costing inline to the market price continuously and severely. The fluctuation of the price of CPO may affect the earning of the
subsidiary (AIL) of 17.31 million Baht and allowance for doubtful accounts of 2.78 million Baht. The fluctuation of CPO price mentioned above had reflected the Company's business operation in the production