structural design is completed and the construction of various buildings has progressed by more than 80% of the total construction. At present, the project is in the process of the development of utility
. Currently, the main structural design is completed and the construction of various buildings has progressed by more than 80% of the total construction. At present, the project is in the process of the
amount of THB 3.55 million (2 installments). The remaining amount to be paid upon the Agreement is THB 5.33 million. Currently, hydraulic platform construction work has progressed to around 50 percent. 4
progressed 62.79% (The construction plan was 62.55%). The commercial operation date is scheduled in the second quarter of 2022. Page 3 1.2 Additional Investments in Joint Ventures - On September 25, 2019, EGCO
Directors’ Meeting No. 5/2018 and PF Board of Directors’ Meeting No. 9/2018. The construction of Carnival Magic Project has progressed by about 98.56% of the total construction, or 84.63% of the total
conceived, by design and location and by mitigation measures, so that it complies with one of the following requirements: o the plant does not entail any deterioration nor compromises the achievement of good
completed and the construction of various buildings has progressed by more than 84.63% of the total construction. At present, the project is in the process of the development of utility system including the
completed and the construction of various buildings has progressed by more than 84.63% of the total construction. At present, the project is in the process of the development of utility system including the
will then enable the achievement of overall growth of the Food Business in a significant manner; whereby the Company is projecting to still achieve an overall TSS growth of 5% - 6% YoY. Outlook for 2018
to achieve COD as scheduled in PPA, and construction cost is in line with the budget approved by lenders. This achievement would enable us to keep record of managing the project to commence COD in time