Declaration (Thai version only) Policy (Thai version only) Report (Thai version only) 26. RENAISSANCE FUND MANAGEMENT LIMITED 23 Jan 2018 Signatory Declaration (Thai version only) Policy (Thai version
intended to strengthen the capacity, expertise and international competitiveness of financial markets and the funds industry in the region.Implementation ProgressThe participating economies have progressed
the project has progressed 99.84% (The construction plan was 100%). Consequently, the project was completed and its operation started on July 20, 2017. - Banpong Utilities Company Limited, (EGCO holds a
Renewable Energy Certificates (REC) concerning its electricity generation output. The construction of the project has progressed 97.99% (The construction plan was 97.46%). The commercial operation date is
31/12/2023 87 MR. CHAIYAPRUEK KUNKANJANATHORN / 26/06/2007 ONE ASSET MANAGEMENT LIMITED 01/03/2021 31/12/2023 88 MR. CHAIYO NGAMVIRIYAPONG / 27/01/2022 RENAISSANCE FUND MANAGEMENT LIMITED 04/07
progressed 91.58% (The construction plan was 91.70%). The commercial operation date is scheduled in the fourth quarter of 2019. - SBPL Project, a project of San Buenaventura Power Ltd., Co., (EGCO holds a 49
Electricite Du Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 98.78% (The construction plan was 98.30%). The commercial operation date is scheduled
with EGAT with the contracted capacity of 1,220 MW and Electricite De Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 94.37% (The
with EGAT with the contracted capacity of 1,220 MW and Electricite De Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 96.36% (The
Certificates (REC) concerning its electricity generation output. The construction of the project has progressed 91.55% (The construction plan was 91.52%). The commercial operation date is scheduled in the fourth