. Currently, the main structural design is completed and the construction of various buildings has progressed by more than 80% of the total construction. At present, the project is in the process of the
amount of THB 3.55 million (2 installments). The remaining amount to be paid upon the Agreement is THB 5.33 million. Currently, hydraulic platform construction work has progressed to around 50 percent. 4
progressed 62.79% (The construction plan was 62.55%). The commercial operation date is scheduled in the second quarter of 2022. Page 3 1.2 Additional Investments in Joint Ventures - On September 25, 2019, EGCO
Directors’ Meeting No. 5/2018 and PF Board of Directors’ Meeting No. 9/2018. The construction of Carnival Magic Project has progressed by about 98.56% of the total construction, or 84.63% of the total
completed and the construction of various buildings has progressed by more than 84.63% of the total construction. At present, the project is in the process of the development of utility system including the
completed and the construction of various buildings has progressed by more than 84.63% of the total construction. At present, the project is in the process of the development of utility system including the
Mini Sugar Free. 9M’19 the Company’s gross margin improved to 34.9%, +320 bps YoY. This level of gross margin has been sustained since Q4’18 thanks to “Fit Fast Firm” project (efficiency improvement and
confectionery showed strong sales growth, led by Botan and Olé, particularly with new products launches, Olé Boost and Olé Mini Sugar Free. In 2019, the Company’s gross margin improved to 34.9%, +250 bps YoY
and Olé Mini Sugar Free. However, the growth was partly offset by the decline in OEM-personal care. 1H’19 the Company’s gross margin improved to 35.0%, +330bps YoY. Gross profit increased by THB 614
ขายแบบ pop-up store, Mini Shop ทีส่ านักงานใหญ ่ ชอ่งทางอคีอมเมริซ์ เป็นตน้ ในชว่งทีผ่่านมา บรษัิทไดม้กีารจัดกจิกรรมดา้นการตลาดเพื่อดงึดดูลกูคา้และรักษายอดขาย รวมทัง้เนน้การขาย สนิคา้ทีเ่ป็นตราสนิคา้ขอ