long-term returns. In 2019, CPN progressed with the following asset enhancement initiatives. Renovation programs of existing malls are under way and expects to be completed in 2019 comprising a
agenda as follows: 5.1 The No.1/2018 Extraordinary General Meeting of Shareholders will be convened at 14.00 hours on Tuesday, 19th June, 2018, at the Emerald Hotel, Petchompoo, 3rd Floor, No. 99/1
structural design is completed and the construction of various buildings has progressed by more than 80% of the total construction. At present, the project is in the process of the development of utility
. Currently, the main structural design is completed and the construction of various buildings has progressed by more than 80% of the total construction. At present, the project is in the process of the
-ออสเตรเลีย คอร์ปอเรชัน่ จํากดั ซึ่งเป็นบรษิัทย่อย เพิม่ขึ้น จํานวน 171.08 ลา้นบาท สาเหตุหลกัเน่ืองจากการเริม่เดนิเครื่องเชงิพาณิชยข์องโรงไฟฟ้าพลงังานลม Mount Emerald และโรงไฟฟ้าพลงังานแสงอาทติย์ Collinsville
amount of THB 3.55 million (2 installments). The remaining amount to be paid upon the Agreement is THB 5.33 million. Currently, hydraulic platform construction work has progressed to around 50 percent. 4
from sales of RAC decreased mainly due to AUD/USD currency depreciation, compared to the same period of the previous year. In addition, Mount Emerald Wind Farm Project generated less electricity than
revenue from sales of RATCH-Australia Corporation Pty Ltd, a subsidiary, in the amount of THB 134.85 million, mainly due to AUD currency depreciation in relative to USD currency. In addition, Mount Emerald
progressed 62.79% (The construction plan was 62.55%). The commercial operation date is scheduled in the second quarter of 2022. Page 3 1.2 Additional Investments in Joint Ventures - On September 25, 2019, EGCO
Directors’ Meeting No. 5/2018 and PF Board of Directors’ Meeting No. 9/2018. The construction of Carnival Magic Project has progressed by about 98.56% of the total construction, or 84.63% of the total