Energy Regulatory Commission (ERC) for final approval. The project targets for 85% contracted by commercial operation date. The construction of the project has progressed 61.24% (The construction plan was
with EGAT with the contracted capacity of 1,220 MW and Electricite Du Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 99.40% (The
-year feed-in tariff PPA, for the sale of electricity by the project with the contracted capacity of 640 MW. The construction of the project has progressed 60.67% (The construction plan was 62.95%). The
progressed 97.45% (The construction plan was 97.09%). The commercial operation date is scheduled in the fourth quarter of 2019. Page 6 - SBPL Project, a project of San Buenaventura Power Ltd., Co., (EGCO holds
significantly progressed to meet the deployment deadline by the end of Y.2020. As soon as the projects are completed, they will help generate other recurring incomes. Unit : million Baht Revenue from Customer
use in solving problems, on which companies shall inform its responsible officers. Also, when critical business functions have been restored to normal, companies shall notify the SEC to acknowlege as
time used or expected to use in solving problems, on which companies shall inform its responsible officers. Also, when critical business functions have been restored to normal, companies shall notify the
program, in which the Company and its affiliated hospitals have been participating in all three types of quarantine programs until the situation has been restored. 2. Healthcare Industry Trend in Thailand
project has entered into the PPA with EGAT with the contracted capacity of 514 MW and EDL with the contracted capacity of 130 MW for 27 years. The construction of the project has progressed 66% (The
with the Energy Regulatory Commission (ERC) for final approval. The project targets for 85% contracted by commercial operation date. The construction of the project has progressed 75.48% (The