and Analysis EXECUTIVE SUMMARY SIGNIFICANT EVENTS ABBREVIATION & OUR PROJECTSFINANCIAL PERFORMANCE FINANCIAL POSITION PROGRESS OF PROJECTS UNDER CONSTRUCTION EXECUTIVE SUMMARY 1 Successful Glow SPP1
. • Total investment: approximately JPY 10,000 million • SCOD: Q4/2017 Project updates: The project progress reached 91.5 %. Main activities in Area B are piling work, structure work and module installation
• There are currently 4 main projects that are under construction including: - Xayaburi Power Company Limited (with 99.4% construction progress) - Rayong Central Utility Plants Expansion Phase (CUP-4) (98.2
the drop in the cost of raw materials of CHPP following the progress of EPC work. However, the proportion of revenue that decreased is larger than the decrease in cost of raw materials, resulting in a
expertise of the company. In addition, solar plants have long-term power purchase agreements, which will continuously generate stable revenues which will support GPSC to have sustainable growth. • Progress
expertise of the company. In addition, solar plants have long-term power purchase agreements, which will continuously generate stable revenues which will support GPSC to have sustainable growth. • Progress
Pittayasophon, provided an update on the progress of the Strong Securities Issuers Project to enhance the quality of listed companies and the duty performance of personnel in the capital market, with the main
-month Periods Ended 30 June, 2020 Page 4 Progress of Projects under Construction (as of June 30, 2020) Nava Nakorn Power Plant (Extension) Type of Power Plant Firm-Cogeneration SPP Power Plant Type of