the project has progressed 99.84% (The construction plan was 100%). Consequently, the project was completed and its operation started on July 20, 2017. - Banpong Utilities Company Limited, (EGCO holds a
significant decreasing of diesel consumption in 2Q2020. In addition, rising of refined glycerine price and sales volume also affected to a higher methyl ester business sales revenue due to growing of refined
Renewable Energy Certificates (REC) concerning its electricity generation output. The construction of the project has progressed 97.99% (The construction plan was 97.46%). The commercial operation date is
which progressed unabatingly. The number of service stations as of the end of Q2/2019 was 1,185 locations. Net Marketing Margin increased from the incessant push to enlarge proportions of retail sales
volume in 1Q2020 by 22,346 tons or 28% , resulted from the official announcement of B10 biodiesel as the mandatory diesel. Although, sales revenue of refined glycerine, by-product of methyl ester and fatty
for the eligibility of projects and assets as well as guidance on the tracking of eligibility status during the term of the bond. Their draft recommendations are refined through engagement with finance
progressed 91.58% (The construction plan was 91.70%). The commercial operation date is scheduled in the fourth quarter of 2019. - SBPL Project, a project of San Buenaventura Power Ltd., Co., (EGCO holds a 49
Electricite Du Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 98.78% (The construction plan was 98.30%). The commercial operation date is scheduled
with EGAT with the contracted capacity of 1,220 MW and Electricite De Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 94.37% (The
with EGAT with the contracted capacity of 1,220 MW and Electricite De Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 96.36% (The