the two languages, the Thai version shall prevail. The objective of this MD&A is to present the information and the explanation of financial status and operating results as of the date hereof. However
at 30 September 2019: Project Project value Sold Tentative Transfer from/ (THB m) Transfer progress The ESSE Asoke 4,923 83% 72%(of project value) The ESSE at Singha Complex 4,347 95% 28%(of project
: - Xayaburi Power Company Limited (with 98.7% construction progress) - Nam Lik 1 Power Company Limited (100% completed, waiting for the certificate of COD) - Rayong Central Utility Plants Expansion Phase (CUP-4
Nakorn Electricity Generating Company Limited (NNEG) Expansion Phase (92.3% construction progress) 2. Rayong Waste to Energy (WTE) (57.5% construction progress) 3. Energy Recovery Unit: ERU Project (29.0
supply phase 1 in June 2018. Source: Project Progress Report As of January 2018 , at the end of 2017 , the reservoir had a capacity of approximately 2.40 million cubic meters Schedule for construction of
• There are currently 4 main projects that are under construction including: - Xayaburi Power Company Limited (with 99.4% construction progress) - Rayong Central Utility Plants Expansion Phase (CUP-4) (98.2
future projects. In terms of the progress on Delisting Tender Offer of GLOW, the process was completed on 2 December 2019 and GLOW has been delisted from being listed on the Stock Exchange of Thailand on
revenue of THB 3,818.1 million, increased 48.2% from the ended of the year 2018 as a result of commercially available for two hotels as part of the Project CROSSROADS Phase 1 which commenced the operation
construction including: - Rayong Central Utility Plants Expansion Phase (CUP-4) (99.7% construction progress) - Nava Nakorn Electricity Generating Company Limited (NNEG) (69.1% construction progress
and communication technology Installation of the New Parliament Phase 1 and Phase 2, the Purchasing and Installation Project of Could system to support the service of the central government cloud of CAT