revenue which is recognized based on the percentage of completion of our hydro power projects in Lao PDR, namely XXHP and Nam Che. ABBREVIATION & OUR PROJECTS EXECUTIVE SUMMARY FINANCIAL PERFORMANCE
FINANCIAL PERFORMANCE FINANCIAL POSITION PROGRESS OF PROJECTS UNDER CONSTRUCTION 3 * primarily include the construction revenue recognizes based on the percentage of completion of hydro power projects in Lao
Q4’2018) primarily due to a record of construction revenue which is recognized based on the percentage of completion of our hydro power projects in Lao PDR, namely XXHP and Nam Che. ABBREVIATION & OUR
No. 10000/003/2020 11th February 2020 Subject: Acquisition of all shares in Nam San 3A Power Sole Co., Ltd. and Nam San 3B Power Sole Co., Ltd. of BCPG Public Company Limited to invest in hydro power
applications are addressed under the Marine Renewables Sector Criteria. These Criteria apply to all land-based hydropower facilities, regardless of type, size or location. Projects must meet all the components
year. Nam Che 1 Hydro Power Plant (Run of the river) with an installed capacity of 15 MW has 87.6% construction progress targeted to commence COD on December 1, 2018. ABBREVIATION & OUR PROJECTSFINANCIAL
primarily due to a record of construction revenue which is recognized based on the percentage of completion of our hydro power projects in Lao PDR, namely Nam Che according to TFRIC 12 – Concession Agreement
PROGRESS OF PROJECTS UNDER CONSTRUCTION 3 * primarily include the construction revenue recognizes based on the percentage of completion of hydro power projects in Lao PDR which offset with the construction
construction revenue which is recognized based on the percentage of completion of our hydro power projects in Lao PDR, namely Nam Che. ABBREVIATION & OUR PROJECTSEXECUTIVE SUMMARY FINANCIAL PERFORMANCE FINANCIAL
the company still has total of 1,045 MW capacity in the pipeline with the SCOD by 2025 which would raise total capacity by 48% to 3,245 MW by 2025 (based on committed projects and their SCOD). SPP