Australia. The project cost is approximately AUD 359 million. It is scheduled to enter construction in the first half of 2019 and is anticipated to commence operations in 2020. 1.3 Signing of financial
scheduled in PPA, and construction cost is in line with the budget approved by lenders. This achievement would enable us to keep record of managing the project to commence COD in time and in budget for 27
started in May 2017, and the Power Plant is expected to commence commercial operation in May 2018. 1.3 Signing of Engineering, Procurement, and Construction Contract of Berkprai Cogeneration SPP Project On
Bt65.7 million on its previously-held equity interest in an associate (KCE America, Inc.) prior to its change in status to that of a subsidiary. This resulted in a decrease in basic earnings per share from
approximately AUD 10 million. It is expected to commence commercial operation within December 2018. 1.1.3 Riau Combined-Cycle Power Plant Project in the Republic of Indonesia On April 7, 2017, RH International
52.30 57.67 (5.37) Earnings before interest and tax 59.91 37.76 22.15 Finance costs 32.05 21.85 10.20 Profit before income tax 27.85 15.91 11.95 Income tax expense 1.92 2.75 (0.83) Total comprehensive
equity proportion is approximately 25 percent). The capacity expansion project is planned to begin construction in August 2018 and is expected to be completed and commence commercial operation
Commercial Bank Public Company Limited (SCB) to form a JV under the name AISCB Co., Ltd. (AISCB) through an investment of Bt300mn. AISCB is expected to commence service early next year with an objective to
scheduled in PPA while the construction cost was also in line with the budget approved by shareholders. This achievement would enable us to keep record of managing the project to commence COD in time and in
Commonwealth of Australia. The project cost is approximately AUD 359 million. It started the construction in 2019 and is anticipated to commence operations in 2021. 1.3 The Progress of Riau Combined-Cycle Power