the project has progressed 99.84% (The construction plan was 100%). Consequently, the project was completed and its operation started on July 20, 2017. - Banpong Utilities Company Limited, (EGCO holds a
unpaid rental fees between the tenants and KPM. In order to complete the transaction, the Company is required to solve the issues of outstanding unpaid rental fees and the future rental fees of the lessees
Renewable Energy Certificates (REC) concerning its electricity generation output. The construction of the project has progressed 97.99% (The construction plan was 97.46%). The commercial operation date is
amounted to 131.44 million baht. Most receivables were undue receivables and the unpaid amount did not exceed three months, which was according to a normal credit term for general clients. • Net land
recognized doubtful account increased amount of 28.55 million Baht from the same period last year which is estimated from unpaid debtor 31.42 million Baht and reversal of doubtful accounts receivable from
% year-on-year to 116.63 million baht. Most receivables were undue receivables and the unpaid amount did not exceed three months, which was according to a normal credit term for general clients
progressed 91.58% (The construction plan was 91.70%). The commercial operation date is scheduled in the fourth quarter of 2019. - SBPL Project, a project of San Buenaventura Power Ltd., Co., (EGCO holds a 49
Electricite Du Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 98.78% (The construction plan was 98.30%). The commercial operation date is scheduled
with EGAT with the contracted capacity of 1,220 MW and Electricite De Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 94.37% (The
with EGAT with the contracted capacity of 1,220 MW and Electricite De Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 96.36% (The