with EGAT with the contracted capacity of 1,220 MW and Electricite De Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 94.37% (The
with EGAT with the contracted capacity of 1,220 MW and Electricite De Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 96.36% (The
Certificates (REC) concerning its electricity generation output. The construction of the project has progressed 91.55% (The construction plan was 91.52%). The commercial operation date is scheduled in the fourth
Energy Regulatory Commission (ERC) for final approval. The project targets for 85% contracted by commercial operation date. The construction of the project has progressed 61.24% (The construction plan was
with EGAT with the contracted capacity of 1,220 MW and Electricite Du Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 99.40% (The
-year feed-in tariff PPA, for the sale of electricity by the project with the contracted capacity of 640 MW. The construction of the project has progressed 60.67% (The construction plan was 62.95%). The
progressed 97.45% (The construction plan was 97.09%). The commercial operation date is scheduled in the fourth quarter of 2019. Page 6 - SBPL Project, a project of San Buenaventura Power Ltd., Co., (EGCO holds
significantly progressed to meet the deployment deadline by the end of Y.2020. As soon as the projects are completed, they will help generate other recurring incomes. Unit : million Baht Revenue from Customer
under the KYC/CDD process; (4) the account is re-activated by a large size of transaction after being inactive for some time; (5) significant amount in terms of size/volume is transacted, which is
securities company, when requested under the KYC/CDD process; (4) the account is re-activated by a large size of transaction after being inactive for some time; (Unofficial Translation) - 8 - (5) significant