progressed 91.58% (The construction plan was 91.70%). The commercial operation date is scheduled in the fourth quarter of 2019. - SBPL Project, a project of San Buenaventura Power Ltd., Co., (EGCO holds a 49
Electricite Du Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 98.78% (The construction plan was 98.30%). The commercial operation date is scheduled
with EGAT with the contracted capacity of 1,220 MW and Electricite De Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 94.37% (The
with EGAT with the contracted capacity of 1,220 MW and Electricite De Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 96.36% (The
Certificates (REC) concerning its electricity generation output. The construction of the project has progressed 91.55% (The construction plan was 91.52%). The commercial operation date is scheduled in the fourth
capacity utilization at all PCB facilities during the first quarter, while defect rates gradually improved and several cost reduction initiatives were taken up. In addition, the THB depreciation and a
defect was caused by the Company’ s production process. However, the Company had set aside the reserve and recognized the cost of such product warranty in the amount of THB 178.69 million in 2018. If the
Energy Regulatory Commission (ERC) for final approval. The project targets for 85% contracted by commercial operation date. The construction of the project has progressed 61.24% (The construction plan was
with EGAT with the contracted capacity of 1,220 MW and Electricite Du Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has progressed 99.40% (The
-year feed-in tariff PPA, for the sale of electricity by the project with the contracted capacity of 640 MW. The construction of the project has progressed 60.67% (The construction plan was 62.95%). The