decrease in unit transferring. There was no project completed construction in Q2/2017 while there was Manor Sanambinnam started transferring in Q2/2016. - Revenues from hotel operations in Q2/2017 amounted
decrease in unit transferring. There was no project completed construction in Q3/2017 while there were M Thonglor10 started transferring in Q3/2016 and Manor Sanambinnam continued transferring since Q2/2016
in condominium projects decreased by 59.89 million baht or 23.30% from 257.03 million baht in Q1/2017 to 197.14 million baht in Q1/2018 due to the decrease of unit transfer in existing completed
increased because the unit sale price decrease as mentioned above. Also, Sweet corn price and can packaging price, which are major portion of costs, increased in year 2018. Gross profit The company has gross
previous year. This was due to revenue from sales was increased slightly and a decrease in unit price. In addition, the increase in cost of sales was affected to decrease in gross profit. (4) Selling
2018 decreased from the decrease in unit transfer of MARQUE Sukhumvit. In 2019 there was transfer in MARQUE Sukhumvit amounted 1,311.99 million baht while there was 4,288.09 million baht in 2018. As of
/2018 due to the decrease in unit transfer in MARQUE Sukhumvit project. As of June 30, 2019, there was 79 million baht of signed contracts not yet recognized as income (Backlog) in MARQUE Sukhumvit
. This was due to revenue from sales was increased slightly and a decrease in unit price. In addition, the increase in cost of sales and erection’s cost was affected to decrease in gross profit. (5
, decreased by Baht 44.22 million or 8.46% from the period of previous year. This was due to a decrease in revenue from sales and a decrease in unit price. In addition, the decrease in cost of sales was not in
outside amounting to Baht 47.8 million. On the other hands, sales of Natural Gas Power Plants decreased by Baht 34.5 million or 6.9% because of decrease in unit rate which is adjusted in line with the