Mr.Anya Khanthavit Mr.Anya Khanthavit, Independent Director of Electricity Generating Public Company Limited [“EGCO”], has the duty to prepare and disclose a report regarding his holding securities
scope of work. In addition, CL did not inform the SEC about the outsourcing. SEC Act S.100 in conjunction with 113 Settlement Committee Meeting No. 2/2025 Settlement Committee Order No. 20/2025 Dated
scope of work. In addition, CL did not inform the SEC about the outsourcing. This case is in the process of inquiry by the inquiry official. SEC Act S.100 in conjunction with 113 Criminal Complaint
the SEC office on March 19, 2021 and the auditor is limited its scope of the review or audit by the GL’s executives of the securities issuer for that the financial statement that caused MD&A for Q3
a building and the installation of electricity-generating machinery at the exaggerated price of 58 million baht. Nongree Power Plants, approved by Mr. Bhusana, paid for the first instalment of 12.48
System Engineering and Service Company Limited (ESES) for the construction of a building and the installation of electricity-generating machinery at the exaggerated price of 58 million baht. Nongree Power
Power Plants Company Limited (a 100-percent subsidiary of IEC) through a contract with ESES for the construction of a building and the installation of electricity-generating machinery at the exaggerated
Limited (a 100-percent subsidiary of IEC) through a contract with ESES for the construction of a building and the installation of electricity-generating machinery at the exaggerated price of 58 million baht
entered into a Power Purchase Agreement ("PPA") No.2 with the Provincial Electricity Authority which was information greatly affecting the value of OSCAR shares. Accordingly, the board of
already entered into a Power Purchase Agreement ("PPA") No.2 with the Provincial Electricity Authority which was information greatly affecting the value of OSCAR shares. Accordingly, the board of