of hydro project in Lao PDR Nam Che 1 hydro power plant (Run of the river) with an installed capacity of 15 MW commenced COD on June 1, 2019 to supply electricity to Electricity du Laos (EDL) under a
% construction progress) 4. GLOW SPP Replacement Project According to the Energy Regulatory Commission (ERC) announced the purchase of electricity from Small Power Producers (SPP) for firm under the category of
gas-fired combined cycle cogeneration power that commenced COD on February 1, 2018. It has an installed capacity of 133 MW and sells electricity to EGAT 90 MW under a 25-year PPA. The Project was able
to IU portion. Development of Solar Projects ERC has announced the qualified project sponsors to enter into Power Purchase Agreement with the electricity distribution authorities (Metropolitan
Energy Services Co.,Ltd. (Paju ES) (EGCO holds a 49.00% ownership interest), located in Gangdong-gu, Seoul, South Korea with a capacity of 19.80 MW. Gangdong will sell electricity to Korea Electric Power
before Interest, Taxes, Depreciation and Amortization EDL = Electricite Du Laos EGAT = Electricity Generating Authority of Thailand ERC = Energy Regulatory Commission EPC = Engineering, Procurement and
) successfully started commercial operation in October 2018. Therefore, total installed capacity of 3 SPP power plants which started commercial operation in 2018 is 399 MW which sell electricity to EGAT at 270 MW
the Small Power Producer (SPP) scheme, and reliable cash flows from long-term power purchase agreements (PPAs) with the Electricity Generating Authority of Thailand (EGAT) and reputable clients. (Please
combined cycle cogeneration power that commenced COD on June 1, 2018. It has an installed capacity of 133 MW and sells electricity to EGAT 90 MW under a 25-year PPA. The project was able to achieve COD as
Power Plant decreased by THB 765 million mainly as a result of lower Energy Payment (EP) received from EGAT corresponding to lower electricity dispatch to EGAT. On the other hand, a portion of the