Net Interest-Bearing Debt to Equity ratio of 0.62x. Subsequent Event: Gulf TS1, the second of the four SPPs to COD this year, achieved COD in July 2017 with a total contracted capacity of 130.0 MW
2017 contracted available hours despite planed major maintenance in 1Q2017. - B.Grimm Power (WHA) 1 performed full year operation in 2017 (COD in November 2016). In addition, Four SPPs (Gulf VTP, Gulf
shareholding 25.01% and 74.99% respectively, achieved COD on November 1, 2017 with a total contracted capacity of 125.0 MW, increasing our Equity MW under Operation further to 478.4 MW. The company recently
Equity holding (%) Contracted Capacity (MW) Equity Capacity (MW) COD Gulf VTP Gas-fired Cogeneration SPP 25.01 130.0 32.5 May 2017 Gulf TS1 Gas-fired Cogeneration SPP 25.01 130.0 32.5 Jul 2017 Gulf TS2 Gas
Prefecture, Japan Contracted capacity : 0.50 MW Installed capacity : 0.65 MW Feed-in Tariff (FiT) : 36 JPY / kWh Commercial operation date : 18 August 2015 Concession life : 20 years 2) Shima Solar Power Plant
the contracted capacity of 90 MW. Additionally, the project has the 7 years contract with industrial user to sell 12 MW of electricity along with 13 tonnes per hour of steam output. The construction of
contracted to the Manila Electric Company (MERALCO) pursuant to a 20 years power supply agreement which is extendable for up to an additional 5 years. Construction works of the project was completed and its
the PPA with EGAT for 25 years with the contracted capacity of 90 MW. Additionally, the project has the 7 years contract with industrial user to sell 12 MW of electricity along with 13 tonnes per hour
higher capital budget framework. As of December 31, 2017, the country’s contracted capacity in EGAT system was 42,433 megawatts, 16,071 megawatts or 37.87 percent of which were generated by EGAT power
project has entered into the PPA with EGAT with the contracted capacity of 1,220 MW and Electricite De Laos (EDL) with the contracted capacity of 60 MW for 29 years. The construction of the project has