. Baht 160 million to Q3 and Q4/2019 as a result of postponed deliveries to Major Projects i.e. The New Parliament Building, The Midfield Satellite Building at Suvarnabhumi International Airport and others
pandemic on the goods deliveries including inbound and outbound shipments to customers getting stranded and delayed during this period. In addition, the delayed deliverables at several of L&E‘s completed
had an extra expenses from a delayed project. Those expenses were composed of both a fine from the delayed project (19.00) million baht and extra cost for the delayed project (3.76) million baht. 2.2 In
one project affecting a reduction of income of Baht 20.51 million and the estimation of penalty charge of one project expected to be delayed affecting a reduction of income of Baht 2.56 million
amortization of intangible assets arising from the purchase of investments in associate companies and the result of associate companies’ delayed revenue recognition due to the delay in delivery of work
previous year, as a consequence of the performance of Advance Power Conversion Company (APCON) performance whose projects had been delayed from the plan resulted in net loss in 2018. Earnings before tax (EBT
85.76% from Q1 year 2017. The reason was the delay on the shipment to customers in the first two months of year 2018. The main raw materials’ crop, which is sweet corn, was delayed due to the weather. The
delayed orders from one major customer in this quarter, but the repeated order will be placed in the next quarter. 2. The company’s consolidated net loss for the period (Q.1) amount -11.20 Million Baht
consisting of Interest expense from bank creditors amount of 23.42 million baht, interest on short-term loans amount of 1.63 million baht, interest of debentures amount of 21.74 million baht, delayed interest
the item of the waste management innovation at net value of Baht 532.30 with its goodwill of Baht 193.09 and liabilities of deferred tax of Baht 106.46 2. Saha-Hydrotek Joint Venture Hydrotek Public Co