, 2017 to Baht 9.87 million for the three-month period financial statement ended March 31, 2018 or Baht 1.44 million higher. On June 15, 2016, the Companies entered into a land sale agreement for 1 plot of
represents decreasing of 1 Million Baht (14%) from Q2/2017. The main cause for the lower net profit is economic in Thailand just recovery, and there is a delayed effect before reaching down to subcontractor
construction projects that are being completed. In some projects, the owners have delayed in the work area handover which prohibit the work. The construction area handover is expected to commence and the work
2020, has increased 418.85 Million Baht or 30.96 percent when compared to the same quarter of 2019. Previously, there are delayed in handling over the construction site, project owner’s overlapping work
Section 112 Securities and Exchange Act B.E. 2535 Section 112. In operating the business of securities brokerage, a securities company shall enter into a written agreement with the customers who
) will have 2 options. 1. The company will pay back the investment with interest of 6.75% per year within 5 years as stated in the agreement. The interest will be applied since the first time of borrowing
one project affecting a reduction of income of Baht 20.51 million and the estimation of penalty charge of one project expected to be delayed affecting a reduction of income of Baht 2.56 million
joint venture was later awarded for the aforementioned project with the contract value of Baht 522.24 million. On July 2018, the first amendment to the agreement has been entered into, which both parties
Q2/2020. Main reasons were delay to start work of new projects and award schedule was delayed by pandamic issue such as Engineering work in their headquater have been delayed. Additional, main
1 -Translation- No. ECF2 046/2562 24 December 2019 Subject: Report of Resolution of Board of Directors' Meeting Re: (1) Disposal of Rights under Loan Agreement, Pledge Agreement and Memorandum of