were made on 2017 financial statement, affecting the statement of financial positions as follow: Asset: Investment in associated companies decreased THB 242 million Shareholders’ Equity: Retained
Nakorn Electricity Generating Company Limited (NNEG) Expansion Phase (92.3% construction progress) 2. Rayong Waste to Energy (WTE) (57.5% construction progress) 3. Energy Recovery Unit: ERU Project (29.0
production capacity of Phase 1 and 2 was expanded, which led to solid revenue growth and profitability. We experienced a number of challenging factors that occurred at the same time, such as production of new
54,750,000 cubic meters per year for phase 1A which has commenced operation since the first quarter of 2019. SDWTP is undergoing the phase 1B expansion of another 54,750,000 cubic meters per year, which is
construction of the new Latkrabang factory was completed and production capacity of Phase 3 was partly expanded, which led to solid revenue growth and profitability. We still experienced a number of challenging
other 3 buildings are still under development. Expected to be completed in 2020. Project the Award Patong Phuket provice, phase 1, which is a condominium unit for sale. Phase 2 is still under development
2019. • The company's project 3 projects under construction as follow: - Nava Nakorn Electricity Generating Company Limited (NNEG) (progress at 85.7%) - Rayong Waste to Energy: WTE (progress at 36.8
: - Xayaburi Power Company Limited (with 98.7% construction progress) - Nam Lik 1 Power Company Limited (100% completed, waiting for the certificate of COD) - Rayong Central Utility Plants Expansion Phase (CUP-4
construction including: - Rayong Central Utility Plants Expansion Phase (CUP-4) (99.7% construction progress) - Nava Nakorn Electricity Generating Company Limited (NNEG) (69.1% construction progress
attributable to the owners of the parent THB 214 million, an earnings per share of THB 0.16, with performance from each business unit as follow: The performance of Refinery and Oil Trading Business Group was