2019. • The company's project 3 projects under construction as follow: - Nava Nakorn Electricity Generating Company Limited (NNEG) (progress at 85.7%) - Rayong Waste to Energy: WTE (progress at 36.8
approaching and lower finance cost as a result of lower floating interest rate. Nava Nakorn Electricity Generating Co. Ltd. (NNEG) Shares of profit from NNEG increased by THB 18 million from Q2/2020 mainly due
% construction progress) - Nava Nakorn Electricity Generating Company Limited (NNEG) (51.7% construction progress) - Integrated waste to energy management project or Rayong Waste to Energy (WTE) (3.16
before Interest, Taxes, Depreciation and Amortization EDL Electricite Du Laos EGAT Electricity Generating Authority of Thailand ERC Energy Regulatory Commission EPC Engineering, Procurement and
Discussion and Analysis ABBREVIATION COD Commercial Operation Date EBITDA Earnings before Interest, Taxes, Depreciation and Amortization EDL Electricite Du Laos EGAT Electricity Generating Authority of
) (87.8% construction progress) - Nava Nakorn Electricity Generating Company Limited (NNEG) (28.3% construction progress) Demand for electricity in 2019 Growth with PDP and PTT GroupNew projects in 2019
will reflect the forecast to be more accurate than the past, that only included three main electricity generators; Electricity Generating Authority of Thailand (EGAT), Provincial Electricity Authority
will reflect the forecast to be more accurate than the past, that only included three main electricity generators; Electricity Generating Authority of Thailand (EGAT), Provincial Electricity Authority
participating profit from investment in associated companies and the joint venture in 2018, compared to the same period last year, comes mainly from the increase in electricity generating to the EGAT’s system of
34.0% compared with the same period of 2019. Furthermore, there was a project utilizing CPO to produce electricity that the crushing mills would supply CPO for Electricity Generating Authority of