reasons; - Sales of units in condominium projects increased by 1,094.02 million baht or 212.09% from 515.82 million baht in Q2/2017 to 1,609.84 million baht in Q2/2018 due to the transfer of new 3 completed
and would be completed in the similar time periods. This caused work overload and shortage of skilled workers Q4/2018 and into Q1/2019, resulting on cost overrun. Discussion and Analysis of the Company
and would be completed in the similar time periods. This caused work overload and shortage of skilled workers Q4/2018 and into Q1/2019, resulting on cost overrun. Discussion and Analysis of the Company
other 3 buildings are still under development. Expected to be completed in 2020. Project the Award Patong Phuket provice, phase 1, which is a condominium unit for sale. Phase 2 is still under development
contracted to the Manila Electric Company (MERALCO) pursuant to a 20 years power supply agreement which is extendable for up to an additional 5 years. Construction works of the project was completed and its
and no additional construction projects in the year present which all projects will be completed in 2020 The third quarter in the year 2019, there was no income from service whereas the previous year
and no additional construction projects in the year present which all projects will be completed in 2020 The third quarter in the year 2019, there was no income from service whereas the previous year
the project has progressed 99.84% (The construction plan was 100%). Consequently, the project was completed and its operation started on July 20, 2017. - Banpong Utilities Company Limited, (EGCO holds a
period of 2017. This is the result of loss from investments in an associate and a joint venture, recorded in the income statement by using equity method. However, the company has fully completed the
changed by more than 20%, comparing to the same period of 2017 which is clarified as below Income : (Unit: Million Baht) Consolidated Separate Y2018 + Increased Y2018 + Increased / -Decreased / -Decreased