(“the Company”) and its Subsidiary (“the Group”) would like to clarify the change in operating result for the year ended 31 December 2018, which net profit has changed more than 20% from the last year as
were acquired in late of 2018 and machines that installed in 2nd Factory and were ready to use in second half of 2018 such as screw flight machine and powder booth system machine. 3. Finance costs
design, work suspension or delay due to change in construction design Many projects are gradually completed. Concurrently, many new projects that have been signed into contract or about to be signed which
until the work is completed as scheduled in April 23, 2018. The result of the lawsuit and the exercise of the Company’s right did not change neither on the Company’s shareholding ratio in NWR-SBCC Joint
employees who require to access document and data from the Company’s central operating system are allowed to come in head office from time to time to reduce the possibility and risk of COVID-19 infection and
and changes and adjustment of the construction design, work suspension or delay due to change in construction design. Many projects are gradually completed. Concurrently, many new projects have been
on the dept cost structure analysis for the investment in the biogas power plant project of Aukkrarawat that the Board of Directors has considered additional facts and the study of the change in cost
on the dept cost structure analysis for the investment in the biogas power plant project of Aukkrarawat that the Board of Directors has considered additional facts and the study of the change in cost
estimation of cost causing loss in such project due to various factors i.e. change of materials suppliers causing higher cost, extension of contract causing higher fixed cost as well as its underestimate cost
distribution of product and equipment, design, assembly and installation, and maintenance service of pure water treatment system; including operate clinical business which dialysis services for kidney patients