can also be categorized by industrial sector in which it invests, for example, if invested in transportation system project, infrastructure fund will be listed under transportation and logistics sector
(gross) supercritical coal-fired power plant, which will be co-located at the same campus of the existing 630 MW (2x315) plant Unit1-2 in Zambales province, Luzon of the Philippines. Power Supply
(MERALCO) pursuant to a 20 years power supply agreement which is extendable for up to an additional 5 years. The construction of the project has progressed 83.98% (The construction plan was 84.12%). The
province of Republic of the Philippines. 455 MW of the plant’s capacity and energy are contracted to the Manila Electric Company (MERALCO) pursuant to a 20 years power supply agreement which is extendable
to a 20 years power supply agreement which is extendable for up to an additional 5 years. The construction of the project has progressed 89.83% (The construction plan was 88.38%). The commercial
to a 20 years power supply agreement which is extendable for up to an additional 5 years. The construction of the project has progressed 93.69% (The construction plan was 92.41%). The commercial
contracted to the Manila Electric Company (MERALCO) pursuant to a 20 years power supply agreement which is extendable for up to an additional 5 years. Construction works of the project was completed and its
and lease back of premises categorized as operating lease in the annual financial statements. The SEC is of the opinion that the above transactions were in fact a collateral loan, not an outright
contain information on the securities to be offered, particularly its special characteristics and risks categorized and detailed in a succinct and comprehensible language, to allow investors to access and
be co-located at the same campus of the existing 630 MW (2x315) plant Unit1-2 in Zambales province, Luzon of the Philippines. Power Supply Agreements for 134 MW has been executed and lodged with the