and dispose of hazardous waste through high temperature power plant(s) as well as to generate and sell electricity. ART is currently in the process of conducting a feasibility study regarding this plan
construction plan was 99.12%). The commercial operation date is scheduled in the fourth quarter of 2019. - SBPL Project, a project of San Buenaventura Power Ltd., Co., (EGCO holds a 49% ownership interest.), is
sheet and cash flow from operations to remain strong, and sufficient to meet its planned investments in future growth opportunities. Table 3: Major Projects Update & Recycling Growth Plan 1 Huntsman
, and sufficient to meet its planned investments in future growth opportunities. Table 3: Major Projects Update & Recycling Growth Plan 1 Huntsman assets’ acquisition completed on 3rd January 2020, total
-year feed-in tariff PPA, for the sale of electricity by the project with the contracted capacity of 640 MW. The construction of the project has progressed 60.67% (The construction plan was 62.95%). The
progress and plan of the project; (b) if project is not on progress as expected, cause and solution as well as effect that REIT is affected or may be affected shall be specified; (3) specify details
” and “Nimit Langsuan” projects and the expansion of DEAN & DELUCA in the United States. Meanwhile, the Company has continued to pay back the loan for “MahaNakhon” project since it started recognizing
expense increased 17.6% year-on-year from Baht 939 million in 2016 to Baht 1,104 million in 2017, primarily attributable to an increase in staff to support our business expansion and the inclusion of
the first 9 months of 2018. The reasons were from the rising in pipeline maintenance, estimate replacement cost and depreciation & amortization from capacity expansion investment. EASTERN WATER
to 400 days of Baht 23.04 million had not been included, the net profit of the Corporate Group for Year 2019 would be Baht 548.27 million or an increase of 29.66 percent. This was due to expansion of