(Translation) Bangkok Expressway and Metro Public Company Limited Management Discussion and Analysis for the Quarter Ended on March 31, 2019 1 Significant events 1. The Extraordinary General Meeting
service for operation of Expressway business consisted of costs of toll, amortization on rights to operate completed expressway sectors and compensation for site acquisition cost. For the first quarter of
(Translation) Bangkok Expressway and Metro Public Company Limited Management Discussion and Analysis for the Quarter Ended on June 30, 2018 1 Significant events 1. On March 30, 2018, Bangkok
(Translation) Bangkok Expressway and Metro Public Company Limited Management Discussion and Analysis for the Quarter Ended on March 31, 2018 1 Significant events On March 30, 2018, Bangkok Expressway
Langsuan Projects. The total interest paid equaled to 288.8 Million Baht, comprising of financing costs of 223.6 Million Baht and capitalized interest of 65.2 Million Baht. According to the joint venture of
Langsuan Projects. The total interest paid equaled to 288.8 Million Baht, comprising of financing costs of 223.6 Million Baht and capitalized interest of 65.2 Million Baht. According to the joint venture of
project, with an installed capacity of 4.8 MW has 6.8% construction progress which is on process of construction site preparation. The project has the scheduled COD by December 2019. B.GRIMM POWER PUBLIC
(Translation) Bangkok Expressway and Metro Public Company Limited Management Discussion and Analysis for the Quarter Ended on June 30, 2017 1 Significant events 1. Bangkok Expressway and Metro Public
(Translation) Bangkok Expressway and Metro Public Company Limited Management Discussion and Analysis for the Quarter Ended on September 30, 2017 1 Significant events 1. Bangkok Expressway and Metro
(Translation) Bangkok Expressway and Metro Public Company Limited Management Discussion and Analysis for the Quarter Ended on September 30, 2018 1 Significant events 1. On March 30, 2018, Bangkok