increased 9.5% y-on-y and 5.2% q-on-q (Baht 903 million in 6M’2018 / Baht 463 million in Q2’2018), primarily due to an increase in operation and maintenance costs arising from the new power plants described
increase in electricity unit sold compared to prior period and partially record of revenue from the new biomass power plants which the Group acquired in the third quarter. 4 Q1-2020Q2-2020Q3-2020Q4-2020 2019
projects with PPA expiration during 2016-2025 to build new power plants under another 25-year period of PPA. On September 27, all 5 replacement projects got the all licenses, permits and acceptance letter
replacement scheme which allows SPP projects with PPA expiration during 2016-2025 to build new power plants under another 25-year period of PPA. All 5 replacement projects are under development process with the
revenue increasing derived from the new biomass power plants which the Group acquired in the third quarter of 2020 and revenue recognition of biomass power plant in Khlong Khlung, Kamphaeng Phet Province
apply for a new power plant license. As a result, the value of the project greatly reduced from the date the company bought the project, the company is of the opinion that if the project has not been sold
plan to draft the new Power Development Plan (PDP) to portray a clear picture of power sector development since some planned power plants in PDP 2015 could not be constructed as planned along with
) the full period contributions from 820 MW expansions in last year and the acquisition of 123 MW Angthong Power in March 2020, 2) continued expansion of industrial user base with 26 MW PPA from new
operations of new power plants and project acquisition described previously. COST STRUCTURE FINANCIAL PERFORMANCE 6 * include the construction cost of Nam Che 1 project in Lao PDR while there was the revenue
(1) there are new power plant projects in the area and the neighboring community which could retrieve waste water from Aukkrarawat may consider retrieving the waste water from such new projects if it