Limited (“the Company”) would like to clarify on the performance and the financial status for Q1/2018 ended March 31, 2018 of the Company and its subsidiaries, as shown below: (Unit: Thousand Baht) Revenues
. Details of the costs involving to the WTGs foundation improvement for Huay Bong 2&3 Wind Farm as at March 31, 2018 are as shown in the table. Description Estimated total improvement cost (as of year 2017
and the announcement of the Stock Exchange of Thailand ’s Board on the disclosure of information and practices of listed companies on connected transactions, B.E. 2546 (2003). The details are shown in
are as shown in the table. D Description Estimated total improvement cost (as of year 2017) Estimate and cost for accounting recorded In Q1‐Q2 2018 Estimated total improvement
year as compared to the same period of last year. Nonetheless, the Company has continuing in enhance its performance and has shown improvements under its business operation consideration. Please be
year 2017 at Baht 9.77 million. Details of the costs involving to the WTGs foundation improvement for Huay Bong 2&3 Wind Farm as at September 30, 2018 are as shown in the table. Description Estimated
to the WTGs foundation improvement for Huay Bong 2&3 Wind Farm as at September 30, 2019 were as shown in the table. Description Estimated total improvement cost (as of year 2018) Estimated and cost for
agreement will be effective for three years from 1 January 2020 to 31 December 2022. The details are shown in the Enclosure. Your acknowledgment of this matter would be appreciated. Sincerely, -Ampawee
the performance and the financial status for the year 2019 ended December 31, 2019 of the Company and its subsidiaries, as shown below: (Unit : Thousand Baht) 2019 2018 Change %Change Revenue 910,707
Details of the costs involving to the WTGs foundation improvement for Huay Bong 2&3 Wind Farm as at December 31, 2019 were as shown in the table. Description Estimated total improvement cost (as of year