engaged in distribution of product and equipment, design, assembly and installation, and maintenance service of pure water treatment system; including operate clinical business which Hemodialysis services
operations of the Group The Group has principally engaged in distribution of product and equipment, design, assembly and installation, and maintenance service of pure water treatment system; including operate
Group The Group has principally engaged in distribution of product and equipment, design, assembly and installation, and maintenance service of pure water treatment system; including operate clinical
. Nevertheless, during the project area development, it was found that the neighboring communities around project materially retrieve less waste water from the project. Based on the inspection, it was found that
. Nevertheless, during the project area development, it was found that the neighboring communities around project materially retrieve less waste water from the project. Based on the inspection, it was found that
. Water supply system investment project to the municipality in Chiang Mai It is an investment in the form of Build Own and Operate (BOO). The value of assets under construction as September 30, 2019 the
less waste water from the project. Based on the inspection, it was found that (1) there are new power plant projects in the area and the neighboring community which could retrieve waste water from
November 30, 2017. Nevertheless, during the project area development, it was found that the neighboring communities around project materially retrieve less waste water from the project. Based on the
within November 30, 2017. Nevertheless, during the project area development, it was found that the neighboring communities around project materially retrieve less waste water from the project. Based on the
total project value of 801.56 million baht, outstanding work value of 356.98 million baht. Investment projects in progress as at March 31, 2018 For the progress of the investment 2 project 1. Water supply