Extraordinary General Meeting of Shareholders No. 1/2020, which is scheduled to be held on 25 February 2020, and seek approval for any person(s) assigned by the Board of Directors to have the authority to perform
ESIE 3 water treatment plant is scheduled to achieve COD in 1Q2020 with capacity of 3,600 cubic meter per day and wastewater treatment plant 1,500 cuber meter per day. WHAUP Nghe An Vietnam water
25-year Power Purchase Agreement (PPA) with the tariff of USD 6.5 cent per kWh. The project was able to achieve COD as scheduled in PPA, and construction cost is in line with the budget approved. Move
%, as a result of higher revenue from GHECO-One, compared to the previous year that had a planned maintenance. Moreover, there has also been a completion of COD of 5 SPPs since the second quarter of 2017
remaining backlogs and inventory from the four property development projects are in total of 13,762 million Baht in which are in process of completion and expected to transfer as planned. 1. As of 31 December
remaining backlogs and inventory from the four property development projects in a total of 15,746 million Baht, which are in process of completion and expected to transfer as planned. 1. As of 31 December
deferred revenue amounting to THB 2,100.6 mm to statement of comprehensive income for this period. • Share of profit from power associates and joint ventures decreased by 53.0%, mainly due to the planned
awaiting to transferred at a total value of 15,686 million Baht. The pending amount are to be recognized as planned. 1. As of 31 March 2019, Details and progress of the Company’s residential projects are as
pending amount are to be recognized as planned. 1. As of 31 March 2019, Details and progress of the Company’s residential projects are as follows: Project Operated By Project Value (MB) Total Units Sales
Baht 52.31 million. The main reason was the decrease in revenue from finance lease contracts in the amount of Baht 29.83 million. Additionally, the shutdowns for planned maintenance were more than those