cycle cogeneration power that commenced COD on October 1, 2018. It has an installed capacity of 133 MW and sells electricity to EGAT 90 MW under a 25-year PPA. The project was able to achieve COD as
combined cycle cogeneration power that commenced COD on June 1, 2018. It has an installed capacity of 133 MW and sells electricity to EGAT 90 MW under a 25-year PPA. The project was able to achieve COD as
FINANCIAL PERFORMANCE FINANCIAL POSITION PROGRESS OF PROJECTS UNDER CONSTRUCTION 11 Nam Che 1 Hydro Power Project Type of Fuel Hydro (Run of the river) Installed Capacity 15 MW Economic Ownership 72.0% SCOD
@egco.com Page 2 Management Discussion and Analysis 1. Significant events in the Third Quarter of 2020 1.1 The progress in construction projects 1.1.1 Project completion - Gangdong Fuel Cell Project (Gangdong
quarter of 2017 showing a decrease of Baht 4.76 million or representing 7.46 % decrease since there have been only 6 ongoing projects whereas a subsidiary had 1 additional ongoing project with its contract
operations. - Sales income SAAM Group’s income from sale of electricity is generated from a 2.0 MW solar power project in Thailand which is operated by SAAM-SP1. In Quarter 1 of 2020, electricity sales are THB
) (0.12%) 0.00 0.00% (0.02) (2,300.00%) Revenue Total revenues from operation of SAAM Group consist of (1) revenues from provision of service and rental including the procurement of project land site and
SEGSD’s indirect ownership interest in Darajat Geothermal Project Unit 2 and Unit 3 from 95% to 99.75% while SEGSD remains to hold 100% indirect ownership interest in Darajat Geothermal Project Unit 1
plots with land plot that Takuni Land has already owned, totaling size approximately 15 Rai, will be developed into residential project for sales. 1. Date to enter into the transaction Takuni Land
whereas no service project in this current year due to all had been completed in 2019. . Investment project on hand as ended 31 March 2020 The progress of 2 ongoing investment projects are as follows: 1