25-year Power Purchase Agreement (PPA) with the tariff of USD 6.5 cent per kWh. The project was able to achieve COD as scheduled in PPA, and construction cost is in line with the budget approved. Move
and the project is expected to commence commercial operation in 2021 as scheduled. Management Discussion and Analysis For the Year Ended December 31, 2019 Page 3 1.4 Commercial Operation Commencement of
62.11%). The commercial operation date is scheduled in the midyear 2019 - Xayaburi Project, a project of the Xayaburi Power Company Limited (Xayaburi), (EGCO holds a 12.50% ownership interest.), is a
support and grow together with us. Commercial operation of ABPR5 From a total of 3 SPP power plants in Amata City Industrial Estate that have scheduled COD in 2018, ABPR5 is the third gas-fired combined
billion from financial institutions to secure liquidity flexibility even if the COVID-19 crisis continues for long time. With the supply chain interruption from COVID-19 impact, scheduled commercial
scheduled date to determine the names of shareholders entitled to receive the interim dividend (Record Date) on August 31, 2020 and scheduled the payment date on September 11, 2020. The annual dividend payout
progressed 97.45% (The construction plan was 97.09%). The commercial operation date is scheduled in the fourth quarter of 2019. Page 6 - SBPL Project, a project of San Buenaventura Power Ltd., Co., (EGCO holds
shareholders who has right to receive the dividend will be on March 23, 2020. The payment date of dividends is scheduled on May 15, 2020 from the Company consolidated net profit that still enjoys the tax
develop our people also impacted to the downside. Finally, higher maintenance costs from scheduled kiln overhauls further contributed to the cost increase. We are confident that the reinforcements made in
terminated, with the Company assuming the rights and responsibilities of control and operation in accordance with the contract until the service is completed, for which the scheduled date is April 23, 2018