2018. The Company will updated and disclose the progress of this transaction to the Stock Exchange of Thailand from time to time. 2. Name of Related Party and its Relationship with the Company Lessee
floors together with 36 residential units. Sellable Area : 18,476 sq. m. Unit Size : 453 – 634 sq. m. Project Value : 2,800 Million Baht Construction Progress : 95% Completed - 3 - Summary of the Financial
its plan for the project at soi Sukhumvit 19 from developing a condominium to develop a 4 stars hotel. The current progress is on design stage and choosing hotel brand operator. The Company targets to
to the changes in the following items: - Property, plant and equipment were 15,891.38 million Baht, increased by 630.43 million Baht mainly from progress of construction including clarified water
inventory as at March 31, 2020 accounts for 24.72 percent of the total assets, of which 23.31 percent are finished products, 17.73 percent are work in progress and 40.46 percent are raw materials. The
was the construction in progress for Carnival Magic project., animals and plants of Baht 55.62 million much of the purchase of animals. Cash and cash equivalents decreased of Baht 106.87 million
Management Discussion and Analysis 1. Significant events in the third Quarter of 2019 1.1 The progress in construction projects 1.1.1 Project completion - SBPL Project, a project of San Buenaventura Power Ltd
. Advance payments for constructions and purchase of fixed assets decreased by Baht 54.4 million from Krabi Solid Waste Power Plant which some progress was done during the period. Rights to service under
decreased by Baht 36.2 million from Krabi Solid Waste Power Plant, which partially progress is done during the period. Rights to service under concession arrangements increased by Baht 508.2 million from
from Krabi Solid Waste Power Plant, which partially progress is done during the period. Rights to service under concession arrangements increased by Baht 712.7 million from concession rights of Krabi