. In addition, Gross Refinery Margin was still at the low level. This has affected the performance of the petroleum related business. However, demand for consumption of finished products see signs of
capacity of 1,400 megawatts (700 megawatts per unit) according to the Power Purchase Agreement. It is scheduled for commercial operation in 2024 and 2025 respectively. At present, the project is in the
Directors’ Meeting No. 9/2017 held on October 8, 2017 at 1.00 pm, at the Company registered office No. 1 TP&T Building 14th Floor, Soi Vibhavadi Rungsit 19, Chatujak Sub-district, Chatujak District, Bangkok
timeline from February 2018 to 1Q2020 and the building will be carried out as planned and expected the new buildings will be ready to be in use in 3Q2021. At present, the Company is now adjusting
for commercial operation in 2024 and 2025 respectively. At present, the project is in the process of preparing the Environmental Impact Assessment. 1.3 Commercial operations of Berkprai Cogeneration SPP
timeline from February 2018 to 1Q2020 and the building will be carried out as planned and expected the new buildings will be ready to be in use in 3Q2021. At present, the Company is now adjusting
approximately at THB 39,248 million. In this regard, the Project Companies shall enter into the Engineering Procurement and Construction Contracts (the “EPC Contracts”) with Toshiba Plant Systems & Services
resolved to approve and propose the 2019 Annual General Meeting of Shareholders of the Business to be held on 23 April 2019 for consideration and approval of the annual dividend for 2018 of the Business at
clearing houses and central securities depositories, and benefits of the public and clients shall be taken into consideration. Said regulations shall include at least the following: (1) policies on
(quarter 1/2018), the Company has total revenues at Baht 106.28 million which increased compared to the same quarter of prior year by Baht 15.72 million or equivalent to 17.36%, generated by the previous